GDM, LLC – Arbor Lake Forest Retail
Contract Amount: $10,000,000
Architect/Engineer: Architects Orange
Project Duration: 6 months
Demolition of 225,000 square feet buildings & 12 acre site, located in Lake Forest, Ca. Construction of on and off site improvements with shops buildings.
Home Depot- Arbor Lake Forest
Contract Amount: $6,300,000
Project Duration: 22 weeks
Construction of New 120,000 square foot Store located in Lake Forest , CA.
Cahan Properties – Sierra Village
Contract Amount: $4,503,000
Architect/Engineer: Architects Orange
Project Duration: 6 months
Complete on and off site improvements and construction of 18,000 square feet of shop buildings for new eight-acre shopping center located in Riverside , Ca.
Ralph's Grocery Company- Store# 98
Contract Amount-$3,900,000
Architect /Engineer: Leidenfrost / Horowitz & Associates, Inc
Project Duration: 24weeks
Construction of New 60,000 square foot store located in Riverside , CA.
Ralph's Grocery Company- Store # 113
Contract Amount: $3,600,000
Architect/Engineer: Perkowitz & Ruth
Project Duration: 24 weeks
Construction of New 60,000 square foot store located in Fontana , CA.
Ralph's Grocery Company- Store # 105
Contract Amount: $3,600,000
Architect/ Engineer: Perkowitz & Ruth
Project Duration: 24 weeks
Construction of New 60,000 square foot store located in San Diego , CA.
Lewis Retail Centers – Sierra Lakes Village
Contract Amount: $6,106,958
Architect/Engineer: Pierce Cooley Architects, Inc.
Project Duration: 5 months
Complete on and off site improvements and construction of 25,000 square feet of shop buildings for new ten-acre shopping center located in Fontana , Ca.
Longs Drug Store – Escondido , CA
Contract Amount: $2,100,000
Architect/Engineer: KKE Architects
Project Duration: 5 months
Demolition of existing shop building and build new 25,000 square feet retail drug store and surrounding site work located in Escondido , Ca.
Fishman Properties Chino Hills, LLC- Retail Shop Building “C”
Contract Amount: $900,000
Architect/Engineer: Briscoe & Briscoe, Inc.
Project Duration: 18 weeks
Construction of a new 7,000 square foot store located in Chino Hills , CA
|